Greatfield and Lydiard Millicent
Address Work Details (Inc Postcode) | Traffic Control | Work Status | Estimated Start Date | Latest/Actual Start Date | Estimated End Date | |
STONE LANE, LYDIARD MILLICENT SN5 3NG | Traffic Control (Two-Way Signals) | Works Stop (With Excavation) | 02/07/21 | 05/07/21 | 07/07/21 | |
CHURCH PLACE, LYDIARD MILLICENT | Road Closure | PERMIT-GRANTED | 26/07/21 | 30/07/21 | 06/08/21 | |
LYDIARD GREEN, LYDIARD MILLICENT | Road Closure | PERMIT-GRANTED | 09/08/21 | 13/08/21 | 27/08/21 | |
The Street, Lydiard Millicent | Road Closure | PA-PERMIT-Requested | 10/08/21 | 16/08/21 | 24/08/21 | |
STONE LANE, LYDIARD MILLICENT | Road Closure | PERMIT-GRANTED | 31/08/21 | 01/09/21 | 02/09/21 | |
HOOK STREET, ROYAL WOOTTON BASSETT | Traffic Control (Multi-Way Signals) | PA-PERMIT-Requested | 03/09/21 | 06/09/21 | 07/09/21 | |
Bury Fields, Lydiard Millicent, Wiltshire | Some Carriageway Incursion | PERMIT-GRANTED | 08/09/21 | 14/09/21 | 21/09/21 | |
Stone Lane, Lydiard Millicent, Wiltshire | Traffic Control (Two-Way Signals) | PERMIT-GRANTED | 22/09/21 | 28/09/21 | 05/10/21 | |
The Street, Lydiard Millicent | Road Closure | PERMIT-GRANTED | 18/10/21 | 22/10/21 | 29/10/21 | |
Park Lane, Lydiard, Wiltshire | Road Closure | PAA-PERMIT-Requested | 01/11/21 | 05/11/21 | 12/11/21 | |
PARK VIEW DRIVE, LYDIARD MILLICENT | Road Closure | PAA-PERMIT-Requested | 15/11/21 | 19/11/21 | 26/11/21 | |